Capitol Construction was thrilled to tackle the unique project of renovating and updating Gate 1 at Clemson’s Memorial Stadium (Death Valley). In the two short months leading up to season kick-off, Capitol Construction was tasked with demolishing the existing gate, columns, concrete sidewalks/steps, pavers, and carefully removing the bronze tiger statue. We then poured back approximately 10 cy of concrete to allow for 12 new ornamental gates and more room outside the stadium for the standing lines of people. Within this area, CC constructed three 12’ tall brick columns with architectural precast caps. To top off the project, we reinstalled the existing pavers in the same pattern as they were before, and, with delicate care, reinstalled the one-of-a-kind bronze Clemson Tiger Statue.